C3+ Pipeline Project
50kms of NPS6 grade 359 carbon steel pipeline was successfully constructed in North Western Alberta in the fall of 2020 for one of our key clients. Manpower peaked at 122 workers and consisted of a mainline crew along with a poor boy crew. Not only was the C3+ Pipeline project constructed ahead of schedule, it was completed with the highest quality, safety, and ethical measures available. Our client called this project their ‘Flagship Pipeline'
Scope of this project
ROW construction and access
102 crossings
• 13 open cut crossings, 89 board crossingsStringing
Bending
Welding
Coating
Lowering in
Back fill
Clay work
Tie-ins